Tamamlanan Projeler
ATAMURAT 500/220/110/35/10kV SWITCHYARD
MARY 500kV Switchyard
MARY FERTILIZER PLANT 220/6.3kV
BUGDAYLY SUBSTATIONS 110/10kV
GÜLBAHAR SUBSTATION 220/110/20 kV
Endüstriyel ve Yüksek Gerilim Projeleri
Endüstriyel Tesis Elektrifikasyon Projeleri
| # | Proje Adı | Detaylar | Yer | Yıl |
|---|---|---|---|---|
| 1 | KAPTAN STEEL FACTORY | 380/35KV Air Installed Type Switchyard and Substation, Civil and Electrical Design, Engineering, Supply, Erection and Test & Commissioning, 2 Each PCS 380KV Line Feeder, 1 Each PCS 380KV Coupling Feeder, 2 Each PCS 380/33KV Transformer Feeder | Tekirdag/TURKEY | 2001 |
Yüksek Gerilim Projeleri
| # | Firma | Müşteri | Proje Detayları | Yer | Yıl |
|---|---|---|---|---|---|
| 1 | ÇALIK HOLDİNG | MINISTRY OF ENERGY & INDUSTRY OF TURKMENISTAN | ASHGABAT TEXTILE FACTORY- 110/10kV AIS with 2X16MVA TRANSFORMERS Design & Engineering, Supply, Installation, Test & Commissioning | TURKMENISTAN (ASHGABAT) | 1999 |